What are the standards for installing a battery swapping system?
Preliminary preparation
Staff: installation workers and professional electricians.
Equipment: a forklift (depending on the situation), an electric drill, an impact drill, and national-standard cable (as required by the manufacturer).
Weather: because the work involves electricity, installation should be avoided on rainy days.
Indoor installation requirements for battery swapping cabinets
-
The swapping area should be separated from other production and living areas by solid walls.
-
The swapping area should not obstruct evacuation routes.
-
When the room temperature in the swapping area reaches 35°C, the exhaust facilities should be started, and the exhaust volume should be calculated as 60 m³/(h·m²).
-
Fire extinguishers or other fire-fighting facilities should be provided, and their configuration should comply with the relevant provisions of GB 50140-2005.
Outdoor installation requirements for battery swapping cabinets
-
The cabinet should be installed on a solid, flat cement floor more than 15 cm thick.
-
Sufficient distance should be left around the cabinet to ensure heat dissipation and maintenance access.
-
A line should be drawn at least 1 m from the front of the cabinet to isolate the swapping area from the parking area.
-
A roof should be erected over the battery swapping system to provide shade and rain protection.